Report_Id:ESTIMATE FINAL updated 6-26-09

Date:08/17/2026

COMMONWEALTH OF KENTUCKY

TRANSPORTATION CABINET


Contract ID 252123 Estimate Number 0008 Estimate Type  FINAL
District Office COVINGTON (06360)  Platt, Michael C.

Contractor EATON ASPHALT PAVING CO INC ADDR SN 0 VC Code KY0028332
AND SUBSIDIARY
136 EAST FROGTOWN ROAD
WALTON , KY , 41094
Pay Period 05/16/2026  TO  06/29/2026
Date Approved 08/16/2026
Primary Proj Number MP01200092501
Project No. FD05 012 0009 000-006
Primary County BRACKEN
Name of Road AA HIGHWAY (KY 9)
Description BEGINNING AT THE MASON/BRACKEN COUNTY LINE EXTENDING NORTH T O 0.149 MILES SOUTH OF KY 19
     
     
Date Let 03/20/2025 Formal Acceptance 04/08/2026
Date Awarded 04/01/2025 Date Work Began 08/21/2025
Date Contract Executed 04/14/2025 Open To Traffic 11/06/2025
Date NTP Issued 04/14/2025 Actual Completion Date 11/06/2025

Current Contract Amount

$1,416,818.55

Total to Date

Prev to Date

This Estimate

Original Amount

$1,416,819.35

Total Earnings

$1,226,177.19

$1,221,109.69

$5,067.50

Percent Complete

86.54

Stockpiled Materials

$0.00

$0.00

$0.00

Funds Available

$190,641.36

Gross Earnings

$1,226,177.19

$1,221,109.69

$5,067.50

Total Change Orders

$-0.80

Other Adjustments

$0.00

$0.00

$0.00

TOTAL

$1,226,177.19

$1,221,109.69

$5,067.50

Contract Id 252123

Change Order Summary

County BRACKEN
Estimate Nbr 0008 Project Number FD05 012 0009 000-006
Contractor EATON ASPHALT PAVING CO INC Period 05/16/2026  TO  06/29/2026
 
 
CHANGE ORDERS HISTORY  
CHANGE ORDER NBR DESCRIPTION STATUS APPROVAL DATE TOTAL CO AMOUNT CONTRACT TIME ADJUSTED
001 merge arrows Approved 11/24/2025 $-0.80 0.0
002 Lot Pay Adjustment OVERRIDE Approved 10/23/2025 $0.00 0.0
003 non-tracking tack Approved 04/01/2026 $0.00 0.0
 
 
 
 

CONTRACT ADJUSTMENTS HISTORY

Contract Adjustments

 

 

Adjustment Description

Est No

Adjustment Amount

Line Item Adjustments History
PROJECT ITEM NBR DESCRPITION TYPE EST NO

ADJ QUANTITY

UNIT PRICE

ADJUSTED AMOUNT

Contract Id 252123

COMMONWEALTH OF KENTUCKY

County BRACKEN
Contract No

TRANSPORTATION CABINET

Primary Project Number MP01200092501
Estimate Nbr 0008 Period 05/16/2026  TO  06/29/2026
Contractor EATON ASPHALT PAVING CO INC
 
Project MP01200092501 Fed/State Project Number FD05 012 0009 000-006 Category
LINE ITEM NUMBER ITEM DESCRIPTION ITEM NO. UNIT PLAN QTY CURRENT QUANTITY QUANTITY PAID THIS EST QUANTITY PAID PREV. EST QUANTITY PAID TO DATE UNIT PRICE AMOUNT PAID THIS EST AMOUNT PAID TO DATE
Project MP01200092501 Fed/State Project Number FD05 012 0009 000-006 Category 0001 PAVING
0005 LEVELING & WEDGING PG64-22 00190 TON 551.00 525.720 0.000 0.000 85.00 0.00
0010 CL2 ASPH SURF 0.38D PG64-22 00301 TON 5,175.00 5,175.000 5,142.690 5,142.690 85.00 437,128.65
0015 ASPHALT MATERIAL FOR TACK 00356 TON 77.00 0.000 0.000 0.000 1.00 0.00
0020 CL3 ASPH SURF 0.38B PG64-22 00388 TON 6,700.00 6,700.000 6,413.550 6,413.550 91.00 583,633.05
0025 TEMPORARY SIGNS 02562 SQFT 140.00 140.000 228.000 228.000 5.00 1,140.00
0030 MAINTAIN & CONTROL TRAFFIC 02650 LS 1.00 1.000 1.000 1.000 19,550.00 19,550.00
0035 PORTABLE CHANGEABLE MESSAGE SIGN 02671 EACH 2.00 2.000 2.000 2.000 1,950.00 3,900.00
0040 MOBILIZATION FOR MILL & TEXT 02676 LS 1.00 1.000 1.000 1.000 4,550.00 4,550.00
0045 ASPHALT PAVE MILLING & TEXTURING 02677 TON 1,360.00 1,360.000 607.230 607.230 23.00 13,966.29
0050 EDGELINE RUMBLE STRIPS 02697 LF 57,000.00 57,000.000 55,429.000 55,429.000 0.17 9,422.93
0055 ARROW PANEL 02775 EACH 1.00 1.000 2.000 2.000 250.00 500.00
0060 PAVE STRIPING-TEMP PAINT-4 IN 06510 LF 217,210.00 217,210.000 152,728.000 152,728.000 0.14 21,381.92
0065 PAVE STRIPING-THERMO-6 IN W 06542 LF 60,000.00 60,000.000 54,897.000 54,897.000 1.05 57,641.85
0070 PAVE STRIPING-THERMO-6 IN Y 06543 LF 56,430.00 56,430.000 47,613.000 47,613.000 1.05 49,993.65
0075 PAVE MARKING-THERMO CURV ARROW 06574 EACH 8.00 8.000 12.000 12.000 110.00 1,320.00
0080 PAVE MARKING-THERMO ONLY 06576 EACH 2.00 2.000 0.000 0.000 300.00 0.00
0085 REMOVE PAVEMENT MARKER TYPE V 06600 EACH 60.00 60.000 60.000 60.000 11.03 661.80
0090 FUEL ADJUSTMENT 10020NS DOLL 18,735.00 18,735.000 775.430 775.430 1.00 775.43
0095 ASPHALT ADJUSTMENT 10030NS DOLL 47,056.00 47,056.000 0.000 0.000 1.00 0.00
0100 CENTERLINE RUMBLE STRIPS 20458ES403 LF 53,048.00 53,048.000 28,681.000 28,681.000 0.18 5,162.58
0105 ELECTRONIC DELIVERY MGMT SYSTEM 26228EC LS 1.00 1.000 0.000 0.000 0.01 0.00
8000 PAVE MARKING-THERMO MERGE ARROW 06578 EACH 0.00 6.000 6.000 6.000 358.00 2,148.00
8001 LOT PAY ADJUSTMENT 10000NS DOLL 0.00 0.001 -7,001.790 -7,001.790 1.00 -7,001.79
8002 ASPHALT MATERIAL FOR TACK NON-TRACKING 24970EC TON 0.00 61.600 26.260 26.260 1.25 32.82
Project MP01200092501 Fed/State Project Number FD05 012 0009 000-006 Category 0002 DEMOBILIZATION
0110 DEMOBILIZATION 02569 LS 1.00 1.000 0.250 0.750 1.000 20,270.00 5,067.50 20,270.00

SUBTOT

$5,067.50

$1,226,177.18

LNNBR STOCKPILE ADJUSTMENTS

UNIT

ADJ. QUANTITY

EST NBR

UNIT PRICE

ADJUSTED AMOUNT

SUBTOT

$0.00